The Dam – “What’s Going On?!” Update 3


Yesterday our MPA President spoke with Fuddy’s boss – Guilford’s plant engineer… it is clear the dam remains a priority and serious business with Guilford even though the operation has relocated to North Carolina and in light of this new development with the broken gate. The concern at present is the amount of water flowing out (too much) and the upcoming hurricane season and inability to control the water flow on a daily basis. Without the gate, the water will be controlled buy removing or inserting boards from the spillway. The boards do allow for lowering and raising but just not the daily fine tuning we are used to. Also the gate cannot be fixed until the lake level is drawn down. Divers inspecting the gate and taking measurements last week noted the incredible force of the water in this area making underwater repairs impossible.

I’ll keep you posted!